Transporting High Load

High Load Request Form

For approval of transport of high load through network area.

HeightMinimum Notice Period
4 - 5.5m 5 working days
5.5 - 6m 15 working days
6m +

To be assessed 30+ Working days

Horizon Networks reserves the right to extend notice periods and decline the requested carriage date.

Please complete the PDF High Load Application form and email to [email protected]

High load transport approval conditions that may be placed on the haulage contractor include:

  • The Haulage contractor is required to measure and record the height of the load in its prior to travel and make this measurement available on request.
  • Route to be followed by the load, if differing from that on the Request.
  • Time of commencement of travel, if differing from that on the Request.
  • Approval, subject to a satisfactory check, prior to the travel period, of all carriageway conductors along the route (to ensure that their spans have not been recently lowered by any outside influence, such as a vehicle strike on poles or by the transport of an unauthorised high load that has snagged and lowered conductors).
  • Where safety distances may not otherwise be maintained, Approval subject to the presence of a network escort vehicle during the transport of the load to ensure that any necessary precautions (e.g., using insulating skids or covers, lifting low voltage conductors) are taken.
  • Where safety distances will be infringed or the conductors pose an obstruction, Approval subject to the presence of a network escort vehicle and a network lines vehicle, complete with competent persons, to carry out all necessary lines work (e.g., lifting high voltage conductors, disconnection, removal, and later reinstatement of conductors).
  • Payment of all charges reflecting the work carried out by the network operator's contractor.